PROCEDURE FOR GRANTING RIGHT OF WAY TO LAY CABLES AND PIPES IN THE STATE
STEP 1
The person/organization shall formally apply to the Agency to dig. The intended length, width and depth of ducting/trenching are to be clearly stated.
STEP 2
Joint inspection by LASIMRA and the applicant to confirm the veracity of the proposed excavation works.
STEP 3
Rates are to be calculated by LASIMRA and forwarded to the applicants. The rates are in 3 parts:
i) Tar cut
ii) Earth cut
iii) Cost of reinstatement/repairs
STEP 4
Payment made by the applicant.
STEP 5
LASIMRA issues letter of permit.
STEP 6
The Agency Team Continues the monitoring of applicants’ field activities.
STEP 7
Repair of dug roads by LASIMRA upon completion of project. In exceptional cases the contractor is allowed to resurface/repair dug roads
STEP 8
Issuance of clearance letter to the contractor after satisfactory completion of road repairs by LASIMRA.